Installing solar panels is a multi-stage process that goes far beyond the day technicians arrive on your roof. From initial planning to the final grid connection, a typical solar project can span several weeks or even months. In fact, reputable sources estimate that the entire solar installation process generally takes between 2 and 6 months for residential systems. Commercial solar projects tend to be larger and more complex, often running 4 to 6 months (or more) from start to finish. The actual panel installation itself is usually the shortest step, often done in just a day or two for homes, but other stages like permitting and utility approvals can introduce significant wait times.
Site Assessment and Initial Planning
The solar process kicks off with a site survey. For most homes the installer books and completes it within about a week. Our technician checks roof condition, sun exposure, shading, structural strength and your fuse board, and the visit itself takes only a couple of hours.
Business surveys are broader. Engineers assess roof or ground space, electrical capacity and daily load, and often run structural calculations for large roofs or planned carports. Allow one to two weeks for this deeper analysis.
System Design and Engineering
Once the survey is complete, engineers get to work on the layout, choosing the number of panels, inverter type, wiring runs and mounting details to satisfy local building and electrical codes. A straightforward home design usually takes two to three weeks, stretching to four if the roof is awkward or a battery is part of the plan.
Commercial systems call for deeper analysis. Larger systems often need professional-engineer-stamped drawings, structural checks and coordination with architects or facility managers. A modest business install might still be designed within a few weeks, but multi-hundred-kilowatt projects can require a month or more for full review and approval.
Permitting and Approvals
Permitting is usually the slowest step in going solar because everything pauses until local officials and the utility give the green light. For most homes, building and electrical permits plus interconnection approval arrive in about two to seven weeks, though backlogs or design changes can push that past eight. We will handle all the paperwork, but once it is filed, you often end up waiting in city or county queues.
Commercial projects face deeper reviews, including zoning, land-use and environmental checks along with a more detailed utility agreement, so permits typically take four to twelve weeks overall, with some sites clearing in as little as two to six weeks when agencies move quickly.
Installation (On-Site Construction)
Once permits are sorted and the kit has arrived, installation kicks off. For most homes the crew can fit panels, wiring and all the other gear in one to three days, sometimes wrapping up a standard 20- to 30-panel system in a single visit. More intricate layouts or jobs that include a battery usually need a second or third day, so hands-on work is still the speediest phase of the whole solar journey.
Commercial schedules hinge on scale. A modest 50 kW rooftop system can be finished in a week or two, while sprawling ground mounts or factory-roof farms covering several acres often take two to six weeks, and sometimes a month or more if roof reinforcement, carport frames, multiple inverters or medium-voltage transformers are part of the brief. Throughout the build the crew sticks to the approved plans, fastening racking to roof timbers or ground posts, securing panels, completing electrical connections and commissioning monitoring gear, all while keeping to strict safety rules and adjusting for weather so progress stays brisk unless an unexpected snag crops up.
Inspection and Building Approval
After installation, the system stays off until a local inspector signs off. Booking and passing this check usually takes one to two weeks, even though the on-site visit lasts only an hour or two while the inspector reviews mounting, wiring and the inverter. If everything meets code, the permit closes; if not, your installer makes corrections then arranges a quick recheck. Commercial sites often need several inspections such as rough electrical, structural and fire safety, but the full review still aims to finish in roughly two weeks, with coordination handled by the installer.
Grid Connection and Permission to Operate (PTO)
After the final inspection the installer submits the paperwork to the utility, which must install or reprogram a bi-directional net meter and verify that the system is safe. Permission to Operate (PTO) generally comes through two to six weeks after inspection, though a busy utility queue can stretch the wait. Home projects are straightforward: once the meter swap and quick test are done, the utility issues PTO and the system can be switched on. Larger commercial systems may require additional utility studies or heavier-duty equipment such as a higher-capacity meter or transfer switch, so PTO can take a little longer or be granted in stages while safety checks continue. Utilities will not let any system run until every safeguard is confirmed, protecting grid stability.
Common Delays and How They Affect Your Timeline
Even the best-planned solar projects can encounter hurdles that affect how long the installation takes. Here are some common delays and challenges:
- Permitting backlogs
Town halls can turn a two-week permit into six or eight. New Jersey is the prime example. Working with an installer who knows the local office, such as Sunwise Energy, helps keep paperwork moving. - Utility queues
Utilities schedule meter swaps and approvals at their own pace. In Pennsylvania the first approval alone averages 23 days, then PTO can add another couple of weeks. Holidays and policy deadlines slow things further. - Weather and seasonality
Snow and biting cold slow roof crews, so winter projects often run longer than summer installs. - Supply chain hiccups
Most panels and inverters arrive within one to four weeks, but popular micro-inverters or batteries like Powerwall can face long back-orders, pushing activation dates back. - Roof or electrical upgrades
Re-roofing or upgrading a 100-amp panel to 200-amp can add a few weeks before solar work starts, especially in older Northeast homes. - Admin extras
HOA sign-offs, slow loan paperwork or mid-project design changes can all trigger re-approvals and fresh waiting periods. Finalize the scope early and keep financing details ready to avoid these stalls.
Conclusion
Planning, permits, installation and grid approval each take time, but every step is essential to keep a solar system safe, compliant and long-lasting. For most homes the process from first survey to switch-on is finished within a few months, while larger commercial sites need a bit more time for design work and utility sign-offs. Once the utility gives the go-ahead, the panels begin turning sunlight into lower bills for decades, proving that a short wait can deliver lasting rewards.
Ready to put your rooftop to work? Book a free consultation, view realistic savings projections, review current incentives and financing options, and get friendly expert guidance through every step of your solar journey.



